day 4

I forgot to place back some flat cables ...;/ and because it was not done at the beginning, it was quite more difficult;>
then was the time for all of the bottom connectors.

Cables back in the right positions.



on the other side we started to thinking of the arrangement of patchbay and the best way to wire
it... we decided to hard wire everything;) looootsss of time to spend on it ;)

day 5..

power supply, WORKS!
master module fitted on the frame, WORKS! ;)
and first 8 channel modules, everything WORKS ;)...

we had to do some work outside the console so that was it for day 5.

Day 6,

all channels are in!! i tested all the channels and wrote down what is working and what
needs to be fixed..

patchbay work in progress!